- When you create a Story, CPS automatically adds a Main Text InCopy asset and sets the asset to the first step in the editorial workflow: WRITE.
To modify the workflow step OR change the person assigned to complete that step, locate the Story assets widget and find the Main Text asset (purple icon). Click the 3-dot menu to the right of the asset and click “Assign to” to edit the Workflow: - The "Edit workflow" dialog box displays:
- Workflow – defines the specific asset workflow to be used (in this case, Text – Main Daily Digital)
**** Do NOT change the Workflow! **** - Step – defines the task to be completed in the workflow, choose the next step to move forward
- Assigned to – defines the assignee for the task (also known as workflow target)
Note: If you are unsure of who to assign to next you can check the Story Team information in the Story widget. - Manual Deadline – enter the deadline date and time for the next task, as this is what will make the task show in the Assignee’s My Tasks widget with a specific due date (otherwise it will still show in an Assignee’s My Tasks widget but will not indicate a specific due date) Note: Dates span from 8PM to 7:59PM as a full day.
- Annotation – enter a version comment here to note necessary information about the specific version.
- Workflow – defines the specific asset workflow to be used (in this case, Text – Main Daily Digital)
- Click Save to complete changes. An email notification is sent to the Assignee letting them know that the Main Text asset has been assigned (targeted) to them in the system.
_____________
From the Status Widget on the Main Text Overview Page
- On the Main Text Overview page, in the Status widget, click the Arrow icon to edit the Workflow and move the asset to the next step:
- "Edit workflow" dialog box appear
- Workflow – Text – Main Daily Digital
- Step – Whatever is next in the workflow
- Assigned to – Whoever is listed in the Story Team metadata
- Manual Deadline – enter the deadline date and time for the next task, as this is what will make the task show in the Assignee’s My Tasks with a specific due date (otherwise it will still show in an Assignee’s My Tasks but will not indicate a specific due date) Note: Dates span from 8PM to 7:59PM as a full day.
- Annotation – enter a version comment here to note necessary information about the specific version.
- Click Save to complete changes.